Base Preparation Guide

A proper preparation of the base pad for your tank will ensure that the installation process goes smoothly. Please follow the guide in this page to prepare your tank base.

Download Base PREPARATION GUIDE

Tank Model Reference Table

MODEL TANK DIAMETER MINIMUM PAD DIAMETER MINIMUM PAD THICKNESS m3 OF SAND/CRUSHER DUST m3 OF BLUE METAL MINIMUM WATER (LITRES)
CT6 3.92m 6.00m  150mm 4.3m3 1.0m3 2,500
CT9 4.70m 6.70m  150mm 5.3m3 1.0m3 4,000
CT12, HGT55 5.49m 7.50m  150mm 6.7m3 1.0m3 5,500
CT15, HGT75 6.26m 8.30m  150mm 8.2m3 1.2m3 7,000
CT20, HGT90 7.06m 9.10m  150mm 9.8m3 1.2m3 9,000
CT25, HGT110 7.84m 9.90m  150mm 11.6m3 1.2m3 11,000
CT30, HGT135 8.63m 10.70m  150mm 13.5m3 1.2m3 13,500
CT35, HGT160 9.41m 11.50m  150mm 15.6m3 1.6m3 16,000
CT41, HGT188 10.18m 12.20m  150mm 17.6m3 1.8m3 18,500
CT48, HGT220 10.99m 13.00m  150mm 20.0m3 2.0m3 21,500
CT54, HGT250 11.77m 13.80m  150mm 22.4m3 2.0m3 24,500
CT60, HGT285 12.55m 14.60m  150mm 25.2m3 2.0m3 28,000
CT70 13.31m 15.40m  150mm 28.0m3 3.0m3 31,500
CT80 14.09m 16.10m  150mm 30.6m3 3.0m3 35,500

1. Pad specifications

The preparation of the pad for your tank is the responsibility of the customer. Our preferred base material is fine crusher dust; however, if crusher dust is not available in your area, please insist on using screened sand from your local area
(please do not use recycled sand as it may contain contaminants). It must be free of sticks, stones, and clay lumps (6mm diameter or less). 

  • Level Pad (+/- 10mm)
  • Minimum thickness of pad is 150mm (or 250mm for RT310 and RT-365)
  • Minimum compaction of 120kPa
  • Dimensions are outlined on the table below
  • Ensure adequate compaction of the sub soil to avoid subsidence for deep pads
  • The customer is required to place an exclusion zone of minimum 20mm Blue Metal/Stone (no clay or concrete) around the base of the tank after installation to prevent erosion and deter rodents from digging around the base

IMPORTANT: If the site is cut and filled to form the base for the tank, ensure there is adequate compaction (minimum allowable bearing pressure of 120kPa) of the sub soil to avoid subsidence.

IMPORTANT: Adequate drainage must be installed to divert water run off away from the tank.

IMPORTANT: If site access or the pad quality is not adequate, it may be necessary to charge an hourly rate of $65.00 per person for our installation team to leave the tank and reschedule the installation (possibly weeks) until the problem is corrected.

2. Site access

  • Please ensure adequate access to the site for a small
    truck or 4WD and trailer, bearing in mind soil and
    weather conditions
  • Vehicle access is to be available within 10 metres of site
  • If unable to meet these requirements, please contact
    your Installer or Install Co-Ordinator to make alternative
    arrangements

3. On the day

Attendance:

  • Whilst not essential due to individual circumstances, we highly recommend meeting the installer on site prior to the install commencing. This will assist in confirming the exact location of all the components and other on-site considerations.

Water:

  • The customer is required to arrange supply of 10% of the full capacity of the tank in litres of water upon completion to stabilise the liner. This is a condition of the warranty and MUST be provided on the day of
    installation.
  • Note: Our Liners are suitable for the storage of water within a pH range of 3-9, and a water temperature of – 6ºc to + 40ºc.

Payment:

A tax invoice will be forwarded upon notification by the installer of Practical Completion.

For full information, please download the Base Preparation Guide Document.